site icon
Contact Us

Our Projects

Craig Lake Wind

Category:

Renewables

Technology:

Wind

Capacity:

246 MW (megawatts) / 815 GWh (gigawatt hours)

Location:

County of Paintearth No. 18, Alberta, Canada

Status:

In Development

Construction Start:

Anticipated to begin Q2 2026

Ownership:

100% ATCO

Customer:

To Be Determined

Craig Lake Wind

The Craig Lake Wind project is proposed as an estimated 246 MW (megawatt) / 815 GWh (gigawatt hours) wind power project in East Central Alberta, Canada. ATCO EnPower and its affiliate, ATCO Renewables Ltd. (ATCO), acquired the lease agreements for the project lands from Suncor Energy Inc. in January 2023. We are continuing with the project planning and development.

The Project

The project is located approximately 70 km north of the town of Hanna, Alberta and approximately 6.3 km east of the town of Castor in the County of Paintearth No. 18, on privately owned land used for agricultural activities and oil and gas production.

ATCO holds lease options on approximately 7,952 hectares (ha) (124 quarter sections) that the project will be developed on, however, the construction and operating areas will occupy a much smaller area within the project area once the footprint and land agreements are finalized. The project construction footprint will be approximately 186.4 ha and the project operation footprint will be 98.4 ha.

The project will consist of up to 43 wind turbines, a collector system, substation, access roads, and a transmission line interconnection. ATCO is currently in the process of choosing a wind turbine manufacturer and model.

Community Benefits

The project is planned with a generating capacity of 246 MW of energy, producing enough power annually to power 125,000 homes and offset 410,000 tonnes of carbon dioxide1. The project will result in many economic benefits for the County of Paintearth, local businesses, and host landowners. 200 to 300 temporary jobs are expected to be created during the construction phase, with additional long-term jobs expected for the operation and maintenance of the facility. During operations, the project is expected to generate an average of approximately $5-million per year during the project life in tax revenue to the County of Paintearth. In addition, host landowners with project infrastructure on their land will receive lease payments.

1 Based on a 2026 Electricity Grid Displacement Factor of 0.4303 tCO2e/MWh (EDF Associates 2023) and 7,200 MWh annually consumed per household (ATCO 2023).

Project Schedule

  Activity / Milestone

  Anticipated Date*

  Stakeholder engagement begins

  February 2024

  Stakeholder Information Session and Open House

  April 25, 2024

  Stakeholder feedback received to incorporate into Project layout

  July 1, 2024

  AUC Application submitted

  October 2024

  AUC Decision

  Q2 2025

  Development Permit Application submitted

  Q2 2025

  Construction starts

  Q2 2026

  Operation starts

  Q2 2027

* Anticipated dates are subject to change 

Stakeholder Engagement

ATCO is asking for your feedback, questions, concerns, and other information that will help inform the layout of the project. ATCO will be including the revised layout in the AUC Rule 007 application for approval to construct, own and operate the project. ATCO plans to submit the AUC Rule 007 application in Q3 2024. Depending on regulatory approvals, construction is planned to start in Q2 2026 and be complete with the project commissioned and the start of operations in Q2 2027.

Project Events

ATCO held a Project Information Session on April 25, 2024, where details about the project were presented, and the development team responded to questions asked.

Contact Us

Your comments and feedback are important to us. Please contact us:

Toll-free at: 1-866-344-0178
Email: ATCORenewables@ATCO.com

Landowner inquiries:
Julia Chavez, Surface Land Lead
Phone: 403-969-8580

General project information, questions, or concerns:
James Guthrie, Manager, Regulatory & Environment
Phone: 403-804-4062

For all sales and offtake inquiries:
Mike Waller, Senior Director, Sales and Marketing
Phone: 587-894-3991

Project Documents

Related Content

adelaide wind farm

Adelaide Wind

atco infrastructure

Forty Mile Wind Phase 1

Privacy PolicyTerms of Use
�Copyright 2024 ATCO Ltd. All rights reserved.

Customers are free to purchase natural gas services or electricity services from a retailer of their choice. For a list of retailers, visit ucahelps.alberta.ca or call 310-4822 (toll free in Alberta).