Fleet North Wind

Category:

Renewables

Technology:

Wind

Capacity:

246 MW (megawatts) / 815 GWh (gigawatt hours)

Location:

County of Paintearth No. 18, Alberta, Canada

Status:

In Development

Construction Start:

To Be Determined

Ownership:

100% ATCO

Customer:

To Be Determined

Fleet North Wind

The Fleet North Wind (previously Craig Lake Wind) project is proposed as an estimated 246 MW (megawatt) / 815 GWh (gigawatt hours) wind power project in East Central Alberta, Canada. ATCO EnPower and its affiliate, ATCO Renewables Ltd. (ATCO), acquired the lease agreements for the project lands from Suncor Energy Inc. in January 2023. We are continuing with the project planning and development.

The Project

The project is located north of the Hamlet of Fleet, Alberta and approximately 6.3 km east of the town of Castor in the County of Paintearth No. 18, on privately owned land used for agricultural activities and oil and gas production.

ATCO holds lease options on approximately 7,952 hectares (ha) (124 quarter sections) that the project will be developed on, however, the construction and operating areas will occupy a much smaller area within the project area once the footprint and land agreements are finalized. The project construction footprint will be approximately 186.4 ha and the project operation footprint will be 98.4 ha.

The project will consist of up to 43 wind turbines, a collector system, substation, access roads, and a transmission line interconnection. ATCO is currently in the process of choosing a wind turbine manufacturer and model.

Community Benefits

The project is planned with a generating capacity of 246 MW of energy, producing enough power annually to power 125,000 homes and offset 410,000 tonnes of carbon dioxide1. The project will result in many economic benefits for the County of Paintearth, local businesses, and host landowners. 200 to 300 temporary jobs are expected to be created during the construction phase, with additional long-term jobs expected for the operation and maintenance of the facility. During operations, the project is expected to generate an average of approximately $5-million per year during the project life in tax revenue to the County of Paintearth. In addition, host landowners with project infrastructure on their land will receive lease payments.

1 Based on a 2026 Electricity Grid Displacement Factor of 0.4303 tCO2e/MWh (EDF Associates 2023) and 7,200 MWh annually consumed per household (ATCO 2023).

Project Schedule

 Activity / Milestone

  Anticipated Date*

  Stakeholder engagement begins

  February 2024

  Stakeholder Information Session and Open House

  April 25, 2024

  Stakeholder feedback received to incorporate into Project layout (Round 1)

  July 1, 2024

  Stakeholder feedback received to incorporate into Project layout (Round 2)

  TBD

  AUC Application submitted

  TBD

  AUC Decision

  TBD

  Development Permit Application submitted

  TBD

  Construction starts

  TBD

  Operation starts

  TBD

* Anticipated dates are subject to change 

Stakeholder Engagement

ATCO is asking for your feedback, questions, concerns, and other information that will help inform the layout of the project. ATCO will be including the revised layout in the AUC Rule 007 application for approval to construct, own and operate the project. While ATCO had targeted to submit the AUC Rule 007 application for the project to the AUC by the end of 2024, we await the outcome of considerable reforms to the electricity market, which are currently being evaluated by the Government of Alberta and the Alberta Electric System Operator.  Following conclusion of this process, which is expected in early 2025, ATCO looks forward to resuming the application process.  Notwithstanding this short delay, ATCO remains committed to development of this Project, which is consistent with ATCO EnPower's purpose of creating inspired energy solutions for a sustainable world.  We look forward to continuing to engage with you as the Project continues to take shape.

Project Events

ATCO held a Project Information Session on April 25, 2024, where details about the project were presented, and the development team responded to questions asked.

Contact Us

Your comments and feedback are important to us. Please contact us:

ATCO Fleet North Wind

Toll-free at: 1-866-344-0178
Email: ATCORenewables@ATCO.com


Landowner inquiries:

ATCO Fleet North Wind

Toll-free at: 1-866-344-0178
Email: ATCORenewables@ATCO.com


For all sales and offtake inquiries, please contact:

Rahul Patel, Senior Manager, Commercial Operations and Development
Phone: 403-803-0348
Email: rahul.patel@atco.com

Project Documents

Related Content

adelaide wind farm

Adelaide Wind

atco infrastructure

Forty Mile Wind Phase 1

Privacy PolicyTerms of Use
�Copyright 2024 ATCO Ltd. All rights reserved.

Customers are free to purchase natural gas services or electricity services from a retailer of their choice. For a list of retailers, visit ucahelps.alberta.ca or call 310-4822 (toll free in Alberta).