CENTRAL EAST TRANSFER OUT TRANSMISSION PROJECT
PROJECT OVERVIEW
ATCO Electric Ltd. (ATCO) and AltaLink Management Ltd. (AltaLink) were both directed by the Alberta Electric System Operator (AESO) to develop portions of the Central East Transfer Out Transmission Project (the Project). The Project is to reinforce and upgrade the transfer-out capability of the transmission system in the central east area to the rest of Albert’s Interconnected Electric System.
ATCO’s approved Project is located between the existing Tinchebray 972S substation near the Village of Halkirk, Alberta and the service territory boundary near the Villages of Alix and Nevis, Alberta. The Project will include the construction of two staged 240-kilovolt transmission lines and alterations to the existing Tinchebray 972S substation.
Details on AltaLink’s portion of the Project can be obtained by contacting AltaLink.
-
TIMELINE
Late 2024 - Major construction activities targeted to start
February 2023 - Pre-construction activities targeted to start
December 2022 - Received direction from AESO to begin stage 1 construction
August 2021 – AUC grants approval for Project
September 2020 - Facility Application and filing with Alberta Utilities Commission (AUC)
January 2019 - Notification to stakeholders
-
PROJECT INFORMATION
January 2023
October 2021
October 2020
August 2020
March 2020
- Selected Route Mosaics
- Facility Detail Maps
- Reference Map
- Overview Map
- Tinchebray Site Layout
- Project Update Notification Package
June 2019
January 2019
- Selected Route Mosaics
- TRANSMISSION PROJECT INFORMATION SHEETS
- EXTERNAL RESOURCES
Questions? For more information on this project, contact ATCO toll-free at
1-855-420-5775 or by email at consultation@atcoelectric.com.