Urban Pipeline Replacement

Northwest Calgary Connector

The Project

ATCO is proposing to install approximately 14 km of natural gas pipeline that will run along the northwest leg of Stoney Trail within the Transportation/Utility Corridor (TUC) and then along 85th Street NW from Scenic Bow Road to Township Road 261A. As well, we are going to be building four above ground facilities as part of the Northwest Calgary Connector.

Schedule

Currently the Northwest Calgary Connector is proposed to begin construction at the end of 2020. Pre-construction activities have already begun, this includes surveying, environmental assessments, geotechnical work and stakeholder consultation.

Spring 2018 to Fall 2020 - Pre-installation activities

Fall 2020  - Construction scheduled to start

Summer 2021 - Restoration activities scheduled to start

Location

Along Stoney Trail within the Transportation/Utility Corridor (TUC) and then along 85th Street NW from Scenic Bow Road to Township Road 261A.

How this will affect you

Residents in the area may notice an increase in construction traffic, noise associated with construction and potentially dust from the installation of the new pipeline.

Public Consultation

Public consultation along the pipeline route started in spring of 2018. Consultants have been going door to door to speak with residents about the project and answer questions.

We hosted open houses on May 30, 2018 at Bearspaw Christian School and  June 20, 2018 at Lynx Ridge Golf Course. 

Door to door consultation was completed for all adjacent residents in 2018.

 

Snapshot


Construction Timeline: 
Fall 2019 - Summer 2021

Location: Along northwest section of Stony Trail (in the TUC), then North along 85 Street NW from Scenic Bow Road to Township Road 261A

Project: UPR

Phase: Planning

 

Project Update Sept. 4, 2019

We submitted our application the AUC on August 22, 2019.

Based on the timelines provided, we expect a decision by Summer 2020.

You can stay up to date with our application by using Proceeding #24827

 

 

Snapshot

Construction Timeline: Fall 2019 - Summer 2021

Location: Along northwest section of Stony Trail (in the TUC), then North along 85 Street NW from Scenic Bow Road to Township Road 261A

Project: UPR

Phase: Planning