• Byford Rail Extension Project

    • WHY IS ATCO INVOLVED?

      ATCO is relocating sections of its high-pressure natural gas pipeline in and around Armadale and Byford to make way for METRONET’s Byford Rail Extension project. For more information on METRONET’s rail redevelopment project, visit metronet.wa.gov.au/projects/byford-extension

    • WHERE WILL ATCO BE WORKING?

      ATCO’s main construction works will occur near to the rail line in both Armadale and Byford city centres. ATCO may also undertake minor works at other sites between Armadale and Byford.

    • WHEN IS THIS HAPPENING?

      Based on our current construction schedule, ATCO’s construction works will begin in Armadale in August 2023 and continue through to October 2023.

      Construction is planned to commence in Byford from October/November 2023 through to 2024.

      More detail on the construction area and timeframes for each city centre is shown below.

    ARMADALE CONSTRUCTION WORKS (UPDATED 14 SEPT)

    Summary: ATCO will commence underground drilling on Aragon Court from Monday, 18 September. Works on Forrest Road (near Abbey and Green Ave) will also start shortly: expect lane closures over the next 4-5 weeks and avoid the area, if possible.

    Aragon Court: Starting on Monday, 18 September ATCO will begin underground drilling to install our pipeline. on Aragon Court. Aragon Court will continue to be a single lane of traffic until drilling and reinstatement activities are complete (around early October).

    Forrest Road: Works on Forrest Road will begin shortly and run through to mid-October. ATCO is required to excavate part of Forrest Road in order to install our pipeline, so expect delays over the next few weeks.

    There is likely to be a small section of Forrest Road near the rail line that will be completely closed for up to one week in early October.

    ATCO recommends avoiding the Forrest Road rail crossing for the next 4-5 weeks and taking detours via Church Ave or Orchard Ave.

    Armadale Works
    Byford Rail Extension Project

    BYFORD CONSTRUCTION WORKS (UPDATED 14 SEPT)

    Summary: Pipeline construction works are planned to start from late October 2023 until February 2024

    Construction works for Byford are planned to commence from late October/early November 2023 and continue into Q1 2024.

    Pipeline construction works will predominantly occur along George St, but will also include a small section of Evans Way and Larsen Road near the rail line.

    Expect traffic management and delays on George Street while works are underway, however businesses will be open and access will be maintained at all times.

    More information will be shared here as we get closer to construction.

    ATCO will hold community engagement sessions along George Street in late October, prior to the works commencing. This is an opportunity for the general public to ask any questions they have about the works. The below table will be updated once venues and dates are confirmed.

    PREVIOUS ENGAGEMENT EVENTS

    ARMADALE COMMUNITY SESSIONS HELD IN JULY

    ATCO held community pop-up sessions in several locations in Armadale to provide more information on our project and help answer questions.

    Date & Time Location

    Monday, 10 July 2023

    12pm to 3pm

    Forrest Rd Farmers Market

    50 Forrest Rd, Armadale

    We will be set up near the main building entrance

    Wednesday, 12 July 2023

    9am to 12pm

    Armadale Central

    10 Orchard Ave, Armadale

    We will be set up inside on the main thoroughfare near BigW

    Friday, 14 July 2023

    9am to 12pm

    Forrest Rd Farmers Market

    50 Forrest Rd, Armadale

    We will be set up near the main building entrance

    Tuesday, 18 July 2023

    3pm to 6pm

    Armadale Central

    10 Orchard Ave, Armadale

    We will be set up inside on the main thoroughfare near Armadale Library

    Thursday, 20 July 2023

    3pm to 6pm

    Jull St Mall

    Corner of Jull St and Commerce Ave

    We will be set up outside opposite Armadale train station

    Byford Rail Extension Project

    FREQUENTLY ASKED QUESTIONS

    • How is ATCO involved in the project?

      ATCO is relocating gas infrastructure in several locations in and around Armadale and Byford to support METRONET’s upcoming Byford Rail Extension (BRE) project. For more information on METRONET’s rail redevelopment project, visit metronet.wa.gov.au/projects/byford-extension

    • What areas are affected by ATCO works?

      Main construction works will occur in Armadale city centre, along Aragon Court and Forrest Road, and in Byford city centre along George St. ATCO may undertake minor works at other sites between Armadale and Byford from July 2023 onwards.

    • When are ATCO works expected to start?

      Based on our current construction schedule, ATCO’s construction works will begin in Armadale in August 2023 and may continue through to October 2023. Construction is planned to commence in Byford from October 2023 through to early 2024.

    • What will be the impact on me?

      If you live, work or attend venues near the construction areas, you may encounter traffic delays and some noise. More detail will be provided to those impacted as work becomes imminent.

    • Will there be impacts to traffic or business access?

      Yes – however this will be minor.

      Traffic management will be in place on all construction sites to ensure the safety of our crews and local traffic. Traffic delays and some noise are expected while works are underway. ATCO will endeavour to keep the community updated on any significant road closures or traffic management impacts. You may also contact us at any time to enquire about our current or planned works using the details located at the bottom of this page.

      Please follow all directions from ground crews and traffic management when navigating near or around a work site.

    • Will there be road closures?

      There may be some temporary lane closures, detours or road closures while work is taking place to ensure the safety of workers, residents and road users. In these cases, notice will be given beforehand and traffic management will be put in place. Please follow any detours that are in place.

    • Will the work be noisy?

      Construction noise during works is expected, but we will do everything we can to reduce the noise of the works during business hours: most likely between 7am and 7pm Monday to Friday.

      Noise management plans will comply with council guidelines.

    • How will the work be done?

      Our process involves using a combination of open trenches and trenchless technology to install gas mains.

      The trenchless method greatly reduces the time needed to complete works as well as reducing the impact to road users and businesses in the area. Traffic controllers will be onsite to ensure local traffic can move safely around the area.

    • Will there be interruptions to gas supply?

      No, there are no planned interruptions to gas supply as a result of these works.

    • Will there be an impact to my verge or property?

      Should you be an affected resident, you will be contacted directly about the impacts to your property.

      Building a pipeline involves digging open the ground to access pipes, valves and pits. This may impact roads, verges, driveways and footpaths.

      We are committed to returning areas affected by our work to as close to their original condition as reasonably feasible. We will work closely with local councils and affected property owners to try to meet restoration expectations wherever possible.

    HAVE ANOTHER QUESTION?

    If you have a question not addressed on our website, or wish to receive construction and traffic management updates, please email communityfeedback@atco.com

    ATCO General Enquiries (weekdays 7am-6pm) on 13 13 56* (TTY: 13 36 77*)

    ATCO Faults & Emergencies (24 hours) on: 13 13 52 (TTY: 13 36 77*)

    * Local call fee from anywhere in WA excluding mobiles.

    ATCO recognises that we are completing works on Whadjuk Noongar Country, and aim to work in such a way that reflects our respect for the Whadjuk Boodja.